Power On the HPE Third-Party Integrated ORv3 Rack
Connecting power to the third-party integrated ORv3 rack involves the following steps and safety precautions to prevent equipment damage and personal injury.
The power shelves are the primary power-delivery subsystems within the rack. Each power shelf houses the PSUs and power controller and interfaces directly with the rack DC busbar.
Input Power Specifications
The HPE third-party integrated ORv3 rack receives power through the installed power shelves. Each power shelf includes a Positronic 7-pin power connector that serves as the interface between the power shelf and the facility power source.
Facility power is connected to each power shelf using an AC power whip. The facility-side connector and power-whip configuration are determined by the available power infrastructure and site requirements.
In a typical deployment, each power shelf is connected to facility power using an AC power whip. Power whips are not supplied as part of the HPE third-party integrated rack solution. You must procure power whips that are compatible with the available facility power connections and power infrastructure.
Typical deployments use 60 A power connections, with 460C9W 60 A three-phase receptacles being a common facility-side connection option.
Connect Power to the Rack
-
Connect the HPE third-party integrated ORv3 rack to earth ground before applying power. See Ground the HPE Third-Party Integrated ORv3 Rack.
-
Ensure that all facility power connections are in place and meet site requirements.
-
Verify that the power shelves, installed PSUs, power controllers, and DC busbar are properly installed.
-
Ensure that all power and data cables are securely connected and free from visible damage.
To connect power to the third-party integrated ORv3 rack:
- Confirm that all personnel are clear of the rack and associated power infrastructure.
- Switch on the facility power.
- Allow the power shelves, PSUs, and power controllers to complete initialization.