Ground the HPE Third-Party Integrated ORv3 Rack
Use the information in this topic to ground the third-party integrated ORv3 rack.
Before connecting facility power to the rack, connect the rack frame to the protective-earth grounding system of the facility.
CAUTION:
Do not connect the rack to power until the rack frame has been connected to the facility's protective-earth grounding system. Operating the rack without a proper earth-ground connection can result in equipment damage and may create an electrical safety hazard.
To ground the third-party integrated ORv3 rack:
Note:
Follow all site-specific grounding requirements, local electrical codes, and data center installation practices when grounding the rack.
- Ensure that the rack has been moved to its final installation location and that the levelers have been lowered to stabilize the rack.
- Connect the rack frame to the facility protective-earth grounding system in accordance with applicable ORv3 rack-grounding requirements, local electrical codes, and site installation practices.
- Verify that the grounding connection is complete and secure before connecting facility power to the power shelves or powering on any rack components.